After screeding and floating, trowelling is the final stage in finishing a concrete slab. It seals the surface, tightens the top layer, and leaves a smooth, durable finish. Done by hand or with a machine, trowelling must be timed just right — too early and the surface tears, too late and it won’t close properly. This guide walks through how to trowel a concrete slab manually or mechanically, so you get professional results every time.
Trowelling comes after floating, once the surface is firm enough to support your tools or machine without sinking. The bleed water should be gone, and the surface should spring back slightly when pressed. Don’t start too soon or you’ll drag the surface — but don’t wait until it’s bone dry either. Timing depends on slab thickness, temperature, and mix design.
Start with a steel hand trowel around slab edges, up against walls, corners, and any detail work. Keep the blade angled slightly (about 20°) and apply firm, even pressure. Work in overlapping passes, removing any lines or imperfections left from floating. Keep edges consistent with the main slab — don’t over-trowel or leave visible transitions.
Once the slab can take weight, use a walk-behind power trowel with finish blades. Start with low blade pitch and overlap passes by 50%. Keep machine speed steady and avoid sharp turns that dig into the slab. Work in a spiral or lane pattern. Listen to the machine — a “slap” sound means you’re digging; a “whirr” means you’re gliding correctly. Adjust pressure as the concrete stiffens.
As the slab hardens, it becomes harder to trowel — but it’s also the moment when burnishing occurs. Each pass makes the surface tighter and glossier. Wait too long and the surface will resist correction. Do too many passes too early and it’ll remain soft. Ideally, make 2–4 passes, increasing pitch and speed each time to burnish the surface without overworking it.
After your final machine pass, inspect for swirls, lap lines, or edging mismatch. Use a hand trowel to blend these areas. Feather over surface transitions and fix small blemishes. If you’re polishing later, this step helps avoid early grinding defects. On outdoor slabs, lightly texture the surface if it needs slip resistance (or broom it after trowel if desired).
Over-trowelling creates a brittle surface that may delaminate or powder later. Signs you’ve overdone it: dark glaze, excessive shine too early, or dust appearing while working. If in doubt, stop — especially with machine trowels. Final passes should refine, not cut. If the slab is going to be sealed or polished, a lightly closed surface is better than glassy.
Once trowelling is done, begin curing straight away — especially in hot or windy conditions. Cover with plastic, use a curing compound, or mist spray for 7 days minimum. Early curing helps lock in hydration and prevents shrinkage cracking. Don’t let the slab dry out now — this is when it builds strength and durability.
If you'd rather skip the stress and get a flawless concrete floor laid by professionals, we’ve got you covered. From precision prep to polished perfection — we handle it all.
Get in touch today for a no-obligation quote on concrete flooring:
Or fill in the form below and we’ll get back to you with honest advice and a competitive quote.