Can You Lay Concrete in Winter? (UK Temperature Guide)

Contact

✔ How to Pour Concrete in Cold UK Conditions

  1. 1

    Check the Forecast — Avoid Sub-Zero Temperatures

    Always check the weather forecast 48–72 hours ahead of your pour. In the UK, the critical cut-off is around 5°C and rising — anything lower, and you risk the water in the mix freezing before the concrete can set. If frost is forecast overnight within the first 24 hours after your pour, delay the job unless you're fully prepared with insulation. Sub-zero temperatures can destroy a slab before it has a chance to harden, leading to surface scaling, poor strength, or total failure. Aim to pour when temperatures are above 5°C and expected to stay there for at least two to three days. Early morning frost followed by sunshine can be manageable, but sustained cold snaps are a red flag. Don’t risk it without a plan in place.

  2. 2

    Use Warm Water and Cold-Weather Additives

    One of the simplest ways to help concrete perform in cold weather is to use warm water when mixing. This raises the initial temperature of the concrete, helping kick-start the hydration process and offsetting the chill from cold aggregates or the ground. You can also use cold-weather additives like accelerators (e.g. calcium chloride, non-chloride alternatives) to speed up setting and reduce the risk of frost damage. These additives are commonly used in winter pours and available from most builders’ merchants. Just be cautious with dosage — too much can affect the finish or rebar corrosion if you're reinforcing. If you’re ordering ready-mix, tell the supplier you need a winter pour and they’ll often adjust the mix accordingly. Getting the mix right is a key step in beating the UK’s unpredictable winter conditions.

  3. 3

    Pour Early in the Day to Maximise Daylight and Warmth

    In winter, daylight is limited — especially in the UK where it gets dark before 4pm. That makes timing your pour even more important. Always aim to pour first thing in the morning so your slab has the warmest part of the day to start setting. Avoid late afternoon pours, as concrete that’s still soft at sunset will be vulnerable overnight when temperatures drop. The ground and air are typically warmer in the late morning and early afternoon, which can give the mix the boost it needs to begin curing properly. Make sure your team is ready to go before the delivery arrives, so there’s no delay getting the concrete placed, finished, and covered if needed. Good timing reduces your risk and helps ensure an even, durable finish — even in cold weather.

  4. 4

    Cover with Insulating Blankets or Sheeting

    Once the concrete is poured and finished, it’s essential to cover it up if temperatures are expected to drop. Use thermal curing blankets, foam insulation boards, or heavy-duty plastic sheeting to trap heat and protect the slab from frost. These covers help hold in the warmth generated during curing and stop cold air or overnight frost from shocking the surface. Don’t let the covering rest directly on the wet concrete — use bricks, timber battens, or buckets to create a tented effect so the surface finish stays clean and undisturbed. If heavy rain or snow is forecast, ensure the cover is waterproof and well-secured. Insulation is one of the most effective tools for winter concrete work — without it, all your other precautions could be undone by one cold night.

  5. 5

    Extend Curing Time and Monitor Surface Temperature

    Cold weather slows everything down — and concrete is no exception. You’ll need to extend your curing time by at least a few extra days compared to a summer pour. Keep the slab covered for a minimum of 5–7 days and monitor surface temperature if possible. The concrete won’t reach full strength until it’s cured properly, and in low temperatures that process takes longer. Avoid walking on the surface too soon, especially if it feels soft or looks patchy. If you’re pouring a slab that will bear weight (e.g. a driveway or base), wait at least 10–14 days before putting any heavy loads on it. Patience during winter curing is key to avoiding surface damage and long-term weaknesses. The extra time you give it now means less chance of cracking or scaling later.

  • Delayed setting time

    Cold temperatures slow down the chemical reaction that makes concrete harden. This means your slab could stay soft for much longer than expected, especially overnight. If it hasn’t set before a temperature drop or frost, it’s far more vulnerable to damage.
  • Poor curing and reduced strength

    If concrete cures too slowly or unevenly in cold conditions, it may never reach its full strength. You could end up with a weaker slab that’s more prone to cracking or crumbling under load — especially in high-traffic areas like driveways or bases.
  • Surface flaking or scaling

    If the surface freezes during the first 24 hours, it can break away from the rest of the slab as it cures. This leads to a flaky or dusty top layer that looks rough and doesn’t hold up well over time, especially with rain or frost.
  • Freezing of water in the mix

    If the temperature drops below 0°C before the concrete sets, the water inside can freeze. This expands within the slab, causing cracks or internal damage that weakens the structure before it even gets going. Avoid pouring when freezing is forecast.
  • Inconsistent finishes or discolouration

    Uneven setting caused by temperature swings or cold spots can lead to blotchy patches, discolouration, or a poor finish. You might notice differences in surface texture, colour, or strength across the same slab if conditions aren't consistent during curing.
🔹 What’s the minimum temperature to pour concrete in the UK?
The absolute minimum is 5°C and rising — both during the pour and for at least 24–48 hours after. If the temperature drops below freezing before the concrete sets, it can ruin the slab. Always check the forecast and prepare with covers or additives if you're cutting it close.
🔹 What happens if concrete freezes before it sets?
If concrete freezes too early, the water inside expands and damages the internal structure. This leads to weak spots, cracks, or a dusty surface layer. Even if it looks fine on top, frozen concrete often won’t reach its full strength — which means the slab could fail over time.
🔹 Can I use warm water or additives in the mix?
Yes — using warm water can help raise the starting temperature of the mix, and cold-weather additives (like accelerators) can speed up setting. Just make sure the mix doesn’t become too hot or set too fast. If you’re using ready-mix, ask the supplier for a cold-weather formulation.
🔹 Should I cancel my pour if frost is forecast?
If frost is likely within 24 hours of pouring and you don’t have proper insulation ready, it’s best to reschedule. One night of freezing temps can undo all your work. But if you’ve got covers, warm water, and additives lined up, you may still be able to go ahead safely.
🔹 How long does concrete take to cure in winter?
In cold weather, curing takes longer — usually 7 days or more for light foot traffic, and up to 14 days before heavy loads like vehicles. Keep the slab covered and insulated for at least the first week. Slower curing is expected, but patience pays off with stronger results.